Procuring for the next phase of a 25 MW group captive solar park in India

Written by
4
min read time
November 16, 2026

A Tier 2 Indian EPC used Odyssey supply-chain credit to procure 7.2 MWp of solar modules and keep its 25 MW solar park on schedule, paying just 15% upfront.

‍

The challenge

The client is building a 25 MW AC solar park in Maharashtra under India's group captive model. Local businesses take an equity stake in the project and buy its power under long-term agreements. Eight off-takers had signed on, from a paper mill and an industrial bearings maker to auto component manufacturers, a hospital and two hotels.

The first 7.5 MW AC was commissioned and synchronised with the state grid in August 2026. Grid connectivity for the full 25 MW was already approved. The next step was 7.2 MWp of new modules.

That is where the money got tight. Module suppliers wanted 100% payment before dispatch. Revenue from the new capacity would only start once it was installed, tested and connected, months later. Like most growing EPCs, the client had more work ready to build than cash to fund it upfront.

The solution

Odyssey bought the modules on the client's behalf and paid the suppliers in full before dispatch. The client paid 15% upfront and repays the balance after 120 days, a term set to match the installation and commissioning schedule.

  1. The client places the order through Odyssey and pays a 15% deposit.
  2. Odyssey pays both module suppliers 100% upfront and holds title to the equipment.
  3. The modules ship to site and the client installs them over about 60 days.
  4. Testing, inspection and grid synchronisation follow, with the new capacity targeted to start generating in early 2027.
  5. The client repays Odyssey at the end of the 120-day term.

Goldi Solar (through King Sol Energy) and Novasys Greenergy were both already on Odyssey's platform, so there was no supplier onboarding to slow things down. This is the client’s 15th transaction with Odyssey, and the decision to approve the deal took less than one week. 

Before approving the deal, Odyssey's credit and environmental and social teams reviewed the project's grid approvals, commissioning certificates, signed PPAs and insurance cover.

The outcome

The client secured 7.2 MWp of modules without tying up the full purchase price, and the park's next phase stayed on schedule. The new capacity is targeted to come online by January 2027.

The client kept its cash free for the rest of the build. The eight off-takers move closer to running on clean, locally generated power at a predictable price.

Why it matters

India's ten largest EPCs build most of the country's solar today. The next wave of growth depends on Tier 2 EPCs and developers like this one, which have strong projects and real customers but limited access to bank credit. Equipment can make up as much as 75% of a project's cost, and suppliers want it paid for long before the project earns anything.

Supply-chain credit closes that gap. Payment terms that follow the project's own cash flows let EPCs build more, and build faster.

About Odyssey

Odyssey is the financial infrastructure for the clean energy transition in emerging markets. Our procurement platform gives EPCs and installers lower equipment pricing and working capital with payment terms aligned to project cash flows. About 6,000 installers, 80+ equipment manufacturers and over $3.5 billion of capital are on the platform today.