Customer background

Our customer is an Abuja-based renewable energy developer and contractor that has been operating since 2017. It has delivered megawatt-scale solar PV and battery storage projects for third parties, runs its projects with a COREN-registered project director and dedicated site managers in each state, and was qualified by Nigeria's Rural Electrification Agency (REA) to build five solar hybrid mini-grids under the World Bank-funded DARES programme. Once the sites are built, the customer will operate them for 20 years.

The challenge

The customer is building five isolated solar hybrid mini-grids across Adamawa and Sokoto states, which together will connect 12,549 households and businesses. The total project cost is  US$3.5 million.

Under the DARES performance-based grant, funding is paid per verified connection once the sites are built and commissioned. That meant the customer had to buy and import all of the generation, storage, metering and distribution equipment up front, months before any grant money would arrive, while working to a grant agreement that requires the sites to be inspected and commissioned by May 2027.

How Odyssey helped

Odyssey is purchasing the core equipment for all five sites: solar modules, inverters, battery storage, backup gensets, conductor and smart metering. Odyssey pays the verified manufacturers directly, so the equipment moves from the factory to the project without the customer having to find the capital first.

Odyssey works alongside a Nigerian bank that is financing the balance of the project, while the customer funds land and civil works itself. The customer reports weekly from procurement through to grant payment. 

The equipment and project

  • Battery storage: 25 Huawei smart string ESS units (LUNA2000 class) with 5 micro-grid controllers
  • Solar modules: 2,843 Jinko 600 Wp monocrystalline modules
  • Smart metering: 12,426 single-phase and 127 three-phase smart meters, 45 data concentrator units and an AMI/STS prepaid vending system from Shenzhen Star and Zhejiang Niyue
  • Inverters: 7 × 100 kW and 13 × 50 kW string inverters
  • Distribution: 250,980 m of 70 mm² AAC conductor for 62.7 km of low-voltage network on 1,792 poles
  • Odyssey-purchased equipment: about US$2.49 million
  • Project size: 1.71 MWp of solar PV and 5.4 MWh of battery storage across five sites
  • Location: Adamawa and Sokoto states, northern Nigeria
  • Timeline: Equipment delivered in December 2026, generation installed and poles erected by January 2027, customers connected by March 2027, and all five sites commissioned by April 2027

The impact

  • A grant-funded project made bankable: Odyssey's equipment financing bridges the gap between buying the equipment and receiving the results-based grant, so the EPC can build all five sites at once.
  • 12,549 new connections: households and businesses in five communities get metered, prepaid electricity from solar hybrid mini-grids.
  • Clean, reliable power: solar PV and battery storage carry the load, with diesel gensets as backup rather than the main source.
  • Tier 1 equipment, paid directly: Odyssey buys from verified manufacturers and pays them directly, so the customer gets the specified equipment on time and to DARES technical standards.
  • A platform for the next portfolio: this is the customer's first isolated mini-grid portfolio under a performance-based grant, and a successful delivery positions it for further DARES rounds.

‍